Penlink Project Makes Significant Progress

Hibiscus Coast App

Sandy Beech

21 December 2024, 1:29 AM

Penlink Project Makes Significant ProgressAerial View of Penlink Project Progress December 2024

Coasties can look forward to a busy year ahead for the Penlink project, with the construction crew returning from their well-deserved break on Monday, 6 January 2025.


The team has made significant progress this year, achieving several milestones.




Some of the highlights include:


  • 780,000 cubic metres of earth moved
  • 295 metres of network drainage pipes installed
  • 1,216 metres of pipe culverts installed
  • Over 3,000 cubic metres of concrete poured for the WÄ“iti River Bridge piers and abutment
  • Duck Creek Road Bridge beams placed, deck poured and barriers installed




To see the progress firsthand, watch the December 2024 aerial flyover of the entire project.